PLANNING
Urbanisation Action Programme of the Zorrotzaurre Integrated Action 1
See the complete the URBANISATION ACTION PROGRAMME OF THE ZORROTZAURRE INTEGRATED ACTION 1
On September 18th, 2013 the Bilbao City Council government committee agreed definitive approval of the Urbanisation Action Programme (PAU) of the Zorrotzaurre Integrated Action 1. With the publication on October 24th of the approval in the Official Bizkaia Gazette the 20 working day period for public exhibition begins.
The PAU is the technical documentation, which determines how Zorrotzaurre is to be managed. It defines the phases of execution, the timetable (setting maximum start and finish dates for the works) and the cost.
Together with the PAU, the Draft Project for the urbanisation of Zorrotzaurre, a requirement of the Basque Country Law on Land Development, was approved.
The approved document indicates that:
– The Zorrotzaurre Integrated Action 1 is divided into 2 Execution Units. The first, of 389,995 m2, includes the entire right bank of the Deusto Canal and the points north and south of the future island. The second unit, of 167,064 m2 is made up of the land situated in the centre of the current peninsula. The Execution Unit 1 is divided into 4 areas for urbanisation purposes.
– With regard to the San Ignacio bridge connection, the document indicates that the works should begin within a maximum of 24 months from definitive approval of the Land Reorganisation Project.
– The estimated cost of the total urbanisation works for the Integrated Action 1 is 197 million Euros, divided into 138 million Euros for the Execution Unit 1 and 59 million Euros for the Execution Unit 2.